Meter-main with feed-through lugs single line diagram
Outdoor meter-main feeding large loads and the interior panel. Use this where the meter and main breaker are combined outdoors in a meter-main, with large loads fed from it directly and feed-through lugs supplying the panel inside.
A free template with typical ratings, conductor callouts and general notes. Open it, change what differs on your job, fill in the title block and export a PDF.
Open this template in the editor Download the SVG
What the reviewer checks on this drawing
The reviewer checks the meter-main as the service disconnect, the interior panel as a subpanel with isolated neutrals, and that the feed-through conductors are protected by the 200A main.
What the drawing shows
Every device on the sheet, in the order power reaches it.
| Symbol | Label | Rating or detail | Conductors feeding it |
|---|---|---|---|
| Utility source | Utility service | 120/240V 1φ 3W | |
| Meter | Meter-main | 200A outdoor · NEMA 3R | Service conductors, per utility |
| Circuit breaker | 200A 2P | Main breaker | |
| Panel | Meter-main distribution | 200A bus · 8 spaces | |
| Circuit breaker | 60A 2P | ||
| EV charger | Level 2 EVSE | 48A | |
| Circuit breaker | 40A 2P | ||
| Load | A/C condenser | ||
| Device | Feed-through lugs (LUGS) | ||
| Panel | Interior panel | 200A MLO · neutrals isolated | 3 #3/0 Cu + #6 G |
| Circuit breaker | Existing | House circuits | |
| Load | Existing loads |
Notes on the sheet
- Meter-main is the service disconnect. Interior panel is a subpanel with isolated neutrals.
- Feed-through conductors are protected by the 200A main breaker.
Diagram is schematic and not to scale. Field-verify existing equipment ratings. Ratings and conductor sizes shown are typical. Confirm against the adopted code, the equipment listing and a load calculation before installation. Code references are to the 2023 NEC and the 2024 Canadian Electrical Code: see references and editions.
Related service and panel drawings
Service and main panel upgrade to 200A
New meter socket, service entrance and 200A panel.
ServiceView drawingPanel upgrade with grounding system replacement
New panel with rods, water bond and intersystem bonding.
ServiceView drawingSubpanel addition
100A four-wire feeder to a new subpanel.
ServiceView drawingFeeder to detached garage or ADU
Underground feeder, building disconnect and local grounding electrode.
ServiceView drawingSee all service and panel single line diagrams, or all 40 templates.