Template · Service and panels

Feeder to detached garage or ADU single line diagram

Underground feeder, building disconnect and local grounding electrode. Use this for a feeder to a separate building such as a garage, a workshop or an ADU: an underground four-wire feeder, a disconnect at the building and a grounding electrode there.

A free template with typical ratings, conductor callouts and general notes. Open it, change what differs on your job, fill in the title block and export a PDF.

Open this template in the editor Download the SVG

Feeder to detached garage or ADU single line diagram: underground feeder, building disconnect and local grounding electrode.
Feeder to detached garage or ADU. 16 devices on an 11 × 17 in sheet with a title block and notes column.

What the reviewer checks on this drawing

The reviewer checks the four-wire feeder with the neutral isolated at the detached building, the local grounding electrode, the building disconnect, and the burial depth for the wiring method.

What the drawing shows

Every device on the sheet, in the order power reaches it.

SymbolLabelRating or detailConductors feeding it
Utility sourceUtility service120/240V 1φ 3W
MeterUtility meter200A socketService conductors, per utility
Circuit breaker200A 2PMain breaker
PanelMain panel200A bus · 120/240V
Circuit breakerExistingBranch breakers
LoadExisting loads
Circuit breaker60A 2PFeeder
Disconnect switchBuilding disconnect60A · at detached structure3 #6 Cu + #10 G, Sch 40 PVC underground
PanelGarage / ADU panel100A MLO · neutrals isolated
GroundGrounding electrodeAt detached structure
Circuit breaker20A 1P
LoadReceptacles
Circuit breaker15A 1P
LoadLighting
Circuit breaker30A 2P
LoadMini-split

Notes on the sheet

  • Four-wire feeder: neutral isolated and equipment ground bonded at the detached structure.
  • Grounding electrode installed at the detached structure and connected to the equipment grounding bar.
  • Burial depth per the adopted code for the wiring method used.

Diagram is schematic and not to scale. Field-verify existing equipment ratings. Ratings and conductor sizes shown are typical. Confirm against the adopted code, the equipment listing and a load calculation before installation. Code references are to the 2023 NEC and the 2024 Canadian Electrical Code: see references and editions.

See all service and panel single line diagrams, or all 40 templates.